Year 7 building project

​As part of preparations to welcome year 7 students to Benowa State High School in 2015 a new multi-storey teaching area has been constructed over 2014.

This page follows the progress of this project with photos and updates over the course of the construction.

Project progression​
19/01/2015 The final details and checks are taking place in preparation for the first day back at school in 2015
18/09/2014 The scaffold has started to come down giving us the first glance at the new building.
14/07/2014 The building has reached its final level as the roof is starting to take shape.
20/03/2014 Exciting progress as the concrete slab is poured.
​​​3/03/2014​ ​​​​​​​Foundation work continues with the first bricks being laid.
​​4/02/2014​

​Ground work has begun on the buildings foundations and footings

​20/01/2014 ​The Christmas school break saw the commencement of the Year 7 Building Project as the excavation and levelling of the site began.​
 ​
​​ ​​ ​​
 